Continuation of wave power experiment, Hanstholm phase 2B
Wave energy test is extended due to an unexpected stop caused by the sinking of the float (due to corrosion). The test is continued in order to obtain sufficient long period of performance data. The float is reinstalled May 24 1995, new data acquisition system established in August 95 and the test demonstrate raliable performance until the test is terminated in January 1996. Incorporating the test results, the energy price is calculated for a 300 MW wave power plant in the Norh Sea
Key figures
Period:
1995 - 1996
Funding year:
1996
Own financial contribution:
0.82 mio. DKK
Grant:
0.70 mio. DKK
Funding rate:
46 %
Project budget:
1.52 mio. DKK
Category
Oprindelig title
Forlængelse af forsøget med bølgeenergi ved Hanstholm, fase 2B
Programme
EFP
Technology
Wave
Project type
Udvikling
Case no.
1363/96-0010
Participants
Danish Wave power ApS (Main Responsible)
Partners and economy
Partner | Subsidy | Auto financing |
---|---|---|
NKT CABLES A/S | ||
Højgaard og Schultz A/S | ||
Flygt Pumper A/S | ||
Rambøll |
Contact
Kontakperson
Nielsen, Kim (Rambøll)
Comtact information
Danish Wave power ApSBredevej 2
DK-2830 Virum, Denmark
Nielsen, Kim (civ.ing., Rambøll); Projektleder: Scholten, Christian (civ.ing., Rambøll), 45986000, kin@ramboll.dk
Øvr. Partnere: NKT A/S; Højgaard og Schultz A/S; Flygt Pumper A/S; Rambøll