Optimized solar heating production in a liberalized electricity market. Demonstration of full-scale plant
The project demonstrates for the first time a combination between CHP and solar power systems.
Results
8,019 m2 solar collectors producing 8% of the annual consumption in Brædstrup and nearly the total consumption on a good summer day were combined with a natural gas-fired CHP plant. An optimised ARCON HT2006 collector was developed for this purpose, and the control system was designed to ensure that supply-pipe temperature from solar collectors is always as low as possible and that the temperature in the existing water storage tank does not drop below 90 deg. C. (Energy 10)
Key figures
Period:
2006 - 2009
Funding year:
2006
Own financial contribution:
0.00 mio. DKK
Grant:
3.62 mio. DKK
Funding rate:
0 %
Project budget:
0.00 mio. DKK
Category
Oprindelig title
Optimeret solvarmeproduktion i et liberaliseret elmarked. Demonstration af fuldskalaanlæg
Programme
ForskEL
Technology
Solar
Case no.
6369
Participants
PlanEnergi (Main Responsible)
Partners and economy
Partner | Subsidy | Auto financing |
---|---|---|
Danmarks Tekniske Universitet (DTU) | ||
ARCON SOLAR A/S | ||
BRÆDSTRUP FJERNVARME A M B A | ||
Rambøll | ||
MARSTAL FJERNVARME A M B A |
Contact
Kontakperson
Sørensen, Per Alex
Comtact information
Øvr. Partnere:
Contact email
pas@planenergi.dk