Optimization and automation of staged gasification plant
This project was meant to develop TK Energi’s stepwise gasification concept and improve full-scale demonstration at a plant in Gjøl. The pilot system was almost completed, but due to a delay, the design and construction of the full-scale system in Gjøl had already been completed. The project would therefore not provide any new knowledge for the Gjøl project, and TK Energi wanted to stop the project stating a major budget overrun and, in their opinion, a waning market for the technology in Denmark. Long-term operation and troubleshooting components and the operating system were thus not implemented.
Key figures
Participants
Partner | Subsidy | Auto financing |
---|---|---|
No entries available. |
Contact
TK Energi AS
Stationsvej 4
DK-4621 Gadstrup, Denmark
Koch, Thomas , 46191554, tk@tke.dk
Øvr. Partnere: Sydkraft Danmark; CEA (FR); NVE-kraftvarmeproduktion