Biogas transmission grid
The project develops and demonstrates a new biogas infrastructure consisting of 35 km biogas grid, connectiong 5 farm biogas plants with Skjern Power Supply. This is the first stage in ''Ringkøbing Skjern model'' where large farms process manure locally - without any road transportation - and simply send biogas to local heat and power plants.
The project is the first step in ''Ringkøbing Skjern model'' connecting more biogas plants and transmitting raw biogas to several consumers in the municipality of Ringkoebing:Skjern. The work program involves planning: Agreements with suppliers and buyers, coordination with authorities, traces, invitation to constructors, development of new components, wells with sensor and pump technology, gas management system and communications and registration system.
The work program leads to establishment of agreements with contractors, starting to establish the grid in May 2012. Results will be used to demonstrate the principle and create foundation for further expansions of biogas transmission grid in Ringkoebing-Skjern in later phases including further ca. 200 km biogas grid. Finally, the results will be used to commercialize the concept through a new subsidiary - Bioenergy Vest innovation - in order to market biogas transmission grids including installations logistics and trade model both at the domestic and the export market
Key figures
Category
Participants
Partner | Subsidy | Auto financing |
---|---|---|
BIOENERGI VEST A/S | 1,57 mio. DKK | 2,12 mio. DKK |
Contact
Bioenergi Vest A/S
Rødkløvervej 4
DK-6950 Ringkøbing
Byberg, Lars , 29635444, lars.byberg@rksk.dk
Øvr. Partnere: Planaction ApS; Blue Planet Innovation ApS; Rhode A/S; HMN Naturgas I/S. MidtNord