Systems with high level integration of renewable generation units

Institut for Energiteknik
The project developed probabilistic methods for optimum operation and planning of contemporary distribution systems, including probabilistic models for wind power, small-scale CHP plants and load. It also performed probabilistic power transmission calculations.
Project description

Operating and control conditions will be studies under varying production and load conditions in a distribution network with a large number of renewable and environmentally-friendly decentral supply units through probabilistic simulation models. This serves as basis for developing operating and control strategies.

Results

The following challenges were studied:

1) optimum power factor in wind turbine operation;

2) probabilistic analysis to solve capacity deficiencies in transformer or gas turbine plants;

3) minimising connection grid costs of wind turbines through cable selection;

4) maximum wind turbine capacity at reactive effect regulation and energy reduction.

Key figures

Period:
2006 - 2009
Funding year:
2005
Own financial contribution:
0.50 mio. DKK
Grant:
1.80 mio. DKK
Funding rate:
78 %
Project budget:
2.30 mio. DKK

Category

Oprindelig title
Systemer med integration af mange vedvarende forsyningsenheder
Programme
Innovationsfonden
Case no.
ENMI 2104-05-0043

Participants

Aalborg Universitet (Fredrik Bajers Vej) (Main Responsible)
Partners and economy
Partner Subsidy Auto financing
Himmerlands Elforsyning

Contact

Kontakperson
Chen, Zhe (prof.)
Comtact information
Aalborg Universitet. Institut for Energiteknik
Pontoppidanstræde 101
DK-9220 Aalborg Ø
www.iet.aau.dk
Chen, Zhe (prof.), 99409255, zch@iet.aau.dk
Øvr. Partnere: Himmerlands Elforsyning
Contact email
zch@iet.aau.dk

Energiforskning.dk - informationportal for danish energytechnology research- og development programs.

Logo innovationsfonden
Logo for EUDP
Logo for elforsk