Wake affected offshore tower and foundation loads
The objective of this project is on basis of simple measurements on 6 turbine towers in the Rødsand 2 wind farm to identify, model and verify the basic mechanisms driving the increased loading experienced by turbines operating in offshore wind farm conditions as compared with solitary wind turbines subjected to an identical ambient wind climate. Sp
Project description
The objective of this project is on basis of simple measurements on 6 turbine towers in the Rødsand 2 wind farm to identify, model and verify the basic mechanisms driving the increased loading experienced by turbines operating in offshore wind farm conditions as compared with solitary wind turbines subjected to an identical ambient wind climate. Sp
Key figures
Period:
2010 - 2016
Funding year:
2010
Own financial contribution:
3.09 mio. DKK
Grant:
2.31 mio. DKK
Funding rate:
43 %
Project budget:
5.40 mio. DKK
Category
Oprindelig title
Tårn,- fundaments- og krøjebelastninger på offshoremøller
Programme
ForskEL
Technology
Wind
Project type
Forskning
Case no.
10546
Dokumenter
Participants
Danmarks Tekniske Universitet (DTU) (Main Responsible)
Partners and economy
Partner | Subsidy | Auto financing |
---|---|---|
Danmarks Tekniske Universitet (DTU) | 1,65 mio. DKK | 0,74 mio. DKK |
E.ON DANMARK A/S | 0,21 mio. DKK | 1,57 mio. DKK |
GRONTMIJ A/S | 0,45 mio. DKK | 0,09 mio. DKK |
Contact
Kontakperson
Larsen, Gunner Chr.
Comtact information
www.vindenergi.dtu.dkLarsen, Gunner Chr. , 46775056, gula@dtu.dk
Øvr. Partnere: Grontmij Carl Bro A/S; E.ON Vind Sverige AB
Contact email
gula@dtu.dk