Grid connection of 500 kWe two-stage gasifier

The objective of the project is to add a time-limited amount to the electricity production settlement price from biomass gasification to allow the project group to demonstrate that, long term, the gasification facility can run commercially sound with supplort only from the general settlement rules
Project description

The objective of the project is to add a time-limited amount to the electricity production settlement price from biomass gasification to allow the project group to demonstrate that, long term, the gasification facility can run commercially sound with supplort only from the general settlement rules

Key figures

Period:
2009 - 2012
Funding year:
2009
Own financial contribution:
5.00 mio. DKK
Grant:
10.00 mio. DKK
Funding rate:
200 %
Project budget:
5.00 mio. DKK

Category

Oprindelig title
Nettilslutning af 500 kWe totrinsforgasser
Programme
ForskEL
Technology
Bio and waste
Project type
Andet
Case no.
10204

Participants

WEISS A/S (Main Responsible)
Partners and economy
Partner Subsidy Auto financing
WEISS A/S 8,85 mio. DKK 1,34 mio. DKK
COWI A/S 0,33 mio. DKK 0,16 mio. DKK
DALL ENERGY ApS 0,16 mio. DKK 0,07 mio. DKK
Hadsund bys Fjernvarmeværk a.m.b.a. 1,11 mio. DKK 11,82 mio. DKK
Danmarks Tekniske Universitet (DTU) 0,40 mio. DKK

Contact

Kontakperson
Skyum, Bjarne
Comtact information

Weiss A/S
Plastvænget 13
DK-9560 Hadsund
www.weiss-as.dk
Tlf.: 96520444

Contact email
bjs@weiss.as.dk

Energiforskning.dk - informationportal for danish energytechnology research- og development programs.

Logo innovationsfonden
Logo for EUDP
Logo for elforsk