Offshore Cable Installation
The purpose is to develop and demonstrate methods for cableinstallation, which via improved cable
fabrication and installation can reduce costs for installation of array-, infield- and export cables in rel. to
Offshore Wind Turbines with 30 % compared to traditionally employed offsh. cable fabrication and
installation techniques. The purpose is further to reduce risk exposure to cable installation
Key figures
Period:
2012 - 2014
Funding year:
2012
Own financial contribution:
9.40 mio. DKK
Grant:
3.13 mio. DKK
Funding rate:
25 %
Project budget:
12.54 mio. DKK
Category
Oprindelig title
Offshore Cable Installation
Programme
EUDP
Technology
Wind
Project type
Udvikling
Case no.
64012-0102
Dokumenter
Participants
SIEMENS WIND POWER A/S (Main Responsible)
Partners and economy
Partner | Subsidy | Auto financing |
---|---|---|
SIEMENS WIND POWER A/S | 1,75 mio. DKK | 5,24 mio. DKK |
NKT CABLES A/S | 1,39 mio. DKK | 4,16 mio. DKK |