Termination of demonstration plant-1300 kWth -Commercial size- Gasification plant
This is a bonus grant due unforeseen costs in the project: “Demonstration of a new gasification plant for district heating” (64010-0100).
Project description
Key figures
Period:
2010 - 2015
Funding year:
2013
Own financial contribution:
4.03 mio. DKK
Grant:
2.92 mio. DKK
Funding rate:
42 %
Project budget:
6.95 mio. DKK
Category
Oprindelig title
Afslutning af demonstrationsanlæg-1300 kWth bioforgasningsanlæg til kraftvarme
Programme
EUDP
Technology
Bio and waste
Case no.
64013-0570
Dokumenter
Participants
BIOSYNERGI PROCES ApS (Main Responsible)
Partners and economy
Partner | Subsidy | Auto financing |
---|---|---|
BIOSYNERGI PROCES ApS | 2,92 mio. DKK | 4,03 mio. DKK |