Electrically upgraded biogas II

To bring the technology readiness level from 6 to 8 by implementing preventive maintenance on BOP components, optimizing control systems, incorporate a final steam clean up, introduce a more cost effective biological sulfur removal unit using enriched air from the SOEC and operate the demonstration plant for at least 4000 hours including transient operation.
Project description
An existing 10 Nm3/h pipeline biogas upgrading plant based on Solid Oxide Electrolysis and catalytic methanation will be optimized with biological sulfur removal, improved SOEC system and optimized maintenance and control schemes in order to demonstrate 4000 operation hours.

Key figures

Period:
2017 - 2021
Funding year:
2017
Own financial contribution:
4.58 mio. DKK
Grant:
6.67 mio. DKK
Funding rate:
59 %
Project budget:
11.25 mio. DKK

Category

Programme
EUDP
Case no.
64017-05164

Participants

HALDOR TOPSØE A/S (Main Responsible)
Partners and economy
Partner Subsidy Auto financing
HALDOR TOPSØE A/S 2,63 mio. DKK 3,94 mio. DKK
Aarhus Universitet 3,83 mio. DKK 0,43 mio. DKK
Nature Energy Construction A/S 0,21 mio. DKK 0,21 mio. DKK

Contact

Kontakperson
John Bøgild Hansen
Comtact information

Haldor Topsøe alle 1

2800 Kgs. Lyngby

22 75 40 72

Contact email
jbh@topsoe.com