PV-CITIES-2012
In connection to agreed Climate plans and low energy building implementation it is proposed to realize best practice building integration of PV systems in Danish cities. There will here be a total amount of PV installations of 255 kWp or approx. 3000 m2 primarily in Copenhagen, Aarhus, Odense and Aalborg.
Project description
In connection to agreed Climate plans and low energy building implementation it is proposed to realize best practice building integration of PV systems in Danish cities. There will here be a total amount of PV installations of 255 kWp or approx. 3000 m2 primarily in Copenhagen, Aarhus, Odense and Aalborg.
Key figures
Period:
2010 - 2015
Funding year:
2010
Own financial contribution:
9.23 mio. DKK
Grant:
2.50 mio. DKK
Funding rate:
21 %
Project budget:
11.73 mio. DKK
Category
Oprindelig title
PV-CITIES-2012
Programme
ForskVE
Technology
Solar
Case no.
10504
Dokumenter
Participants
Cenergia Energy Consultants (Main Responsible)
Partners and economy
Partner | Subsidy | Auto financing |
---|---|---|
Cenergia Energy Consultants | 0,80 mio. DKK | 0,75 mio. DKK |
Dansk Solcelleforening | 0,10 mio. DKK | 0,02 mio. DKK |
Eniig a.m.b.a. | 0,49 mio. DKK | 1,54 mio. DKK |
European Green Cities | 0,28 mio. DKK | 0,04 mio. DKK |
Solar City Copenhagen | 0,56 mio. DKK | 1,15 mio. DKK |
Teknologisk Institut | 0,08 mio. DKK | 0,02 mio. DKK |
Contact
Kontakperson
Vejsig Pedersen, Peder
Comtact information
CENERGIA Energy Consultants
Herlev Hovedgade 195, st
DK-2730 Herlev
www.cenergia.dk
Vejsig Pedersen, Peder , 44660099, pvp@cenergia.dk
Øvr. Partnere: Teknologisk Institut; Dansk Solcelleforening; Solar City Copenhagen; Foreningen Bæredygtige Byer og Bygninger; EnergiMidt