The project measured switch transients and voltage quality for three different turbine types in three offshore wind farms: Nysted, Horns Rev and Burbo Banks. The project documented voltage conditions
The object of the project was to furnish a dimensioning basis for future offshore wind turbine foundations. This work contributed to greater understanding of erosion conditions around monopole
The object of the project was to develop an experimental method for estimating the modal properties of wind turbines during operation. OMA (Operational Modal Analysis) proved suitable for
This project is one of several projects with the common purpose of predicting electricity generation from a wind farm for up to 48-60 hours based on meteorological forecasts.
The annex will give the participants an overview of the technical and environmental assessment challenges encountered in offshore applications and help them to understand the areas of further R and D
The project included the second phase of a process aimed at establishing a platform for wind turbine simulation as a prerequisite for advanced electrical design and optimisation.
The aim of the project is to develop, verify and implement a detailed physical model for the wind field in a wind farm. The model will allow for detailed aeroelastic simulation of wind turbines sited
The overall objective of the project is to ensure the development of an aetoelastic design complex, which can create the basis for the nest generation of wind turbines and make new design trends
This project, HAVDIM2004, aimed primarily at analysing already accessible measurement data from the two Danish offshore wind farms Horns Rev 1 and Nysted Offshore Wind Farm. The project focused on
This project demonstrated that further improvement and automation of wind power predictions within a 48-hour horizon is possible if the underlying tools such as WPPT (Wind Power Prediction Tool)
The object of this project was to show the existence of high-frequency fluctuations. The measurement of these fluctuations and the subsequent frequency analyses revealed that these frequencies may be
The object was to improve existing PARK models for calculating array losses for wind farms with focus on large offshore wind farms. The project shows that intelligent use of the model parameters
The compiled measuring results and modelling tests produced a scientifically founded basis for providing recommendations for future offshore wind farms in respect of mutual distances between farms and
The project establishes a new model of the Danish electricity system in the form of two buses (east and west Denmark), to which new models of load and production units are connected in the form of
The main points of the project are: 1) Improved methods for modelling of vertical and horizontal variation of wind speeds. 2) Verification, calibration and improvement of acoustic sensors for remote
The object of the research-project is to select which methods will give the best simulation of environmental influence in relation to the geographical placing of the mills, to be able to select what